| March
7 , 2003
Construction:
The
snows of February were a real challenge to the OCC project
team. Getting to work was difficult if not impossible on several
days. Frigid conditions brought some aspects of the project
to a temporary standstill because some materials, like masonry,
cannot be worked with in freezing temperatures. But according
to project supervisor Leonard Copeland of Bovis Lend Lease,
subcontractors on the job and the entire project team are
making up the time lost. "We've got a lot cut out for
us but we'll make it," he said.
Here's
a glance at this week's construction schedule:
- Workers
began installing the Exterior Finish Insulating System (EFIS),
which creates a tan-colored band at the top of the building.
- 75
percent of the windows are now in place.
- On
the 1st floor, 75 percent of the ductwork is completed.
Copper shielding for the MRI is being put in place.
- On
the 2nd floor, workers were hanging ceiling grid and priming
walls for painting.
- On
the 3rd floor, workers began hanging drywall.
- The
sprinkler and fire protection systems on the 2nd and 3rd
floors have been installed and were tested by the manufacturer
and local authorities. Installation of safety systems on
the 1st floor began this week.
Design:
Exterior
signage proposals were reviewed by the Albemarle County Architectural
Review Board, for the visual and aesthetic impact along the
major entrance corridor Route 250. Work continues with the
signage firm Corbin on directional signage along interior
roadways and parking lots, as well as wayfinding signage inside
the building.
Operations:
Martha
Jefferson Hospital's outpatient Cardiopulmonary Rehabilitation
program and outpatient Physical and Occupational Therapy will
find a new home on the 2nd floor of the OCC, next to the Outpatient
Surgery Center. Together, Cardiopulmonary Rehab and PT/OT
will gain efficiencies and provide more comprehensive patient
care. Cardiopulmonary Rehab is currently operating out of
ACAC Fitness and Wellness Center in Albemarle Square, and
PT/OT is located in the Cardwell Center of the Hospital. Both
services will share 10,000 sq. ft., more than doubling the
amount of space they currently have. Both staffs are looking
forward to working together, and patients will enjoy spectacular
views from the 2nd floor windows as they exercise and receive
therapy.
|